Euroget accuses Akufo-Addo of illegality in Sewua Hospital commissioning

.
Euroget De-Invest S.A., the contractor responsible for the construction of the 250-bed Ashanti Regional Hospital in Sewua, has raised serious concerns about the commissioning of the project.

On January 4, President Nana Addo Dankwa Akufo-Addo officially commissioned the Ashanti Regional 250-bed hospital and the 50-bed Infectious Disease Centre in Sewua.

However, in a statement issued shortly after the commissioning, Euroget De-Invest S.A. claimed that the event violated the terms of their contract.

The contractors stated that they had not received full payment for the hospital’s construction and emphasized that the project remains incomplete. They also clarified that the hospital has not been officially handed over to the government.

“As the contractor, we retain possession of the site until the project is handed over correctly and legally. We categorically did not grant permission to any party to enter the site for commissioning purposes.”

Euroget De-Invest accused President Akufo-Addo of engaging in illegality, calling on the relevant authorities to investigate this matter thoroughly.

“Why would an outgoing President engage in such illegality just three days before handing over office?”

Together with the 50-bed Infectious Disease Centre – one of 12 facilities built with COVID-19 funding across the country to manage infectious diseases, the facility, which now stands as the biggest regional hospital across the country, serves as a vital lifeline for the region, bridging gaps in healthcare delivery and ensuring that people of the region have unimpeded access to universal health coverage and improved health outcomes.

This modern health facility is fully equipped with an administration block, out-patients department, physiotherapy, gynaecology wards, sterilization, intensive care unit, maternity and delivery suites, laboratory, pharmacy, theatre complex, laundry and a medical gas plant for the production of medical gases.

The project is part of the nine Euroget hospital projects initiated by former President John Agyekum Kufuor in 2008.

The nine Euroget Hospitals are the 500-bed Military Hospital at Afari, in Kumasi, the 160-bed Wa Regional Hospital, the 250-bed Ashanti Regional Hospital at Sewua, and the 100-bed Ga East Municipal Hospital at Kwabenya.

In addition to these five 60-bed Hospitals at Tepa, Konongo, Twifo Praso and Madina are also part of the project.

Read below the statement by Euroget De-Invest S.A

PRESS RELEASE

FOR IMMEDIATE RELEASE

DATE:5TH JANUARY 2025

CONCERNS OVER THE COMMISSIONING OF ASHANTI REGIONAL 250-BED HOSPITAL IN SEWUA

From the Office of Dr. Said Deraz, Group Chairman, Euroget De-Invest S.A.

The recent commissioning of the 250-bed Ashanti Regional Hospital in Sewua, Bosomtwe District, by President Nana Addo Dankwa Akufo-Addo on Saturday, 4th January 2025, raises serious concerns regarding legal and contractual obligations. While we acknowledge the importance of healthcare infrastructure in the Ashanti Region, we must firmly state that the commissioning of the 250-bed facility Regional hospital was conducted in direct violation of the terms of our contract.

It is important to stress that Euroget De-Invest S.A. has not yet received full payment for the construction of the hospital. Furthermore, the project remains incomplete and has not yet been officially handed over to the government. As the contractor, we retain possession of the site until the project is handed over correctly and legally. We categorically did not grant permission to any party to enter the site for commissioning purposes.

Dr. Said Deraz, Group CEO and Chairman of Euroget De-Invest S.A., expressed his concerns, as below:

“Euroget did not give anyone permission to enter the site. Possession is still ours until we hand it over in the correct and legal manner.”

He further emphasised:

“This is a breach of the contract. We haven’t handed over, and every step should be taken to claim damages against all previous commissioning because, by this action, the President is implying that he could have commissioned those hospitals without incurring any costs on our part.”

The fact that the government proceeded with the commissioning without consulting Euroget raises questions about the adherence to legal protocols and the sanctity of contracts. The company, which secured the funding for the hospital’s construction, was not consulted regarding this purported commissioning. Additionally, there was no representative from Euroget present at the event, which accentuates our exclusion from a critical milestone in the project.

We believe that the government’s actions constitute a serious breach of security concerning the hospital. Entering the premises without our permission to undertake the commissioning, while the hospital remains incomplete and without the contractor being fully compensated, reflects a disregard for the law and contractual agreements. This situation represents a level of lawlessness that cannot be overlooked.

As we approach the transition of power in Ghana, we are left questioning the motives behind such an action. Why would an outgoing President engage in such illegality just three days before handing over office? We must stress that the timing of this commissioning raises concerns about the legitimacy of the actions taken and whether they serve any political agenda rather than the interests of the citizens who rely on these healthcare facilities.

It is fundamental for all stakeholders, including the public, to understand the implications of these actions. The commissioning of the Ashanti Regional 250-bed Hospital should be a moment of pride and achievement for all involved; however, it has instead become a source of contention and uncertainty. We urge the government to respect the rule of law and adhere to the contractual obligations it has entered into.

We call upon the relevant authorities to investigate this matter thoroughly. The actions taken by the government not only undermine the integrity of the project but also set a worrying precedent for future government contracts and projects. The people of the Ashanti Region deserve better than to have their healthcare infrastructure embroiled in legal disputes and contractual violations.

In conclusion, Euroget De-Invest S.A. remains committed to completing the Ashanti Regional 250-Bed Hospital to the highest standards and fulfilling our contractual obligations. We hope that this situation can be resolved amicably and that the government will recognise the importance of following due process in all its dealings. We are prepared to take all necessary steps to protect our rights and seek damages for any breaches of contract that have occurred.

We appreciate the ongoing support from the community and stakeholders, and we will keep the public informed about any developments regarding this matter.

Signed,

Dr. Said Deraz

Group Chairman

Euroget De-Invest S.A.


Sourcecitinewsroom 6th January 2025 8:44 AM

Subscribe to receive breaking news from us.

DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of WikiGhana.

Related to this story

Comments 0

Login and you would be notified when you are mentioned in a comment